Home > PRODUCTS > Finishing Materials > Interiors
BTS Marble Marble Plus Pearl Shining
Fine Stone Embossing coat AG CERAMIC COAT
BTS (Baroco Triple System) Travertine  
 
The luxurious sustainable finish material to replace the interior materials such a stone materials and tiles is the premium
interior finish material to make any color or atmosphere naturally applicable.
In addition, it keeps excellent water-resistance, durability, anti-flammability and anti-discoloration
 
Construction Method
1. Remove out any dust, floating matters, and foreign materials on the surface.
2. Do the repair work for the cracks or the damaged parts of the surface, using Baro Putty, to make the surface smooth.
3. Apply Primer to the whole surface, using a roller or a spray, to strengthen the adhesiveness.
4. Discuss PVC joint sealant and joint interval with the owner of a building in advance prior to the construction work.
5. Strongly adhere the joint sealant by use of a caulking material so that the joint sealant wont fall off.
6. Remove the joint sealant cover after spraying BTS marble.
7. You can mix a hardener for dryness and workability on a jobsite
8. Do the necessary curing work in advance to prevent a finishing material from flying out.
9. Use a spray gun to apply. The nozzle diameter for the spray gun should be 6-10mm and its pressure for use should
be 3-5kgf/cm².
10. During the BTS Marble spraying work, the color and the pattern can become different so test it in advance.
11. Do the construction work after the color primer-applied surface is completely cured. 90° When using a spray gun, be sure
to make the right angle (90) on the surface.
12. Put BTS marble into a BTS gun and apply it on the whole in the thickness of 1.5mm for small particle-patterns.
13. 12 hours later, check the dryness conditions of the surface.
14. Polish the surface for smoothness, using an electric sander or an air sander.
15. After polishing is completed and the surface is completely dried, apply a coating material to the surface, using a roller or
a spray.
16. In case you have to stop the work in the middle, be careful not to make any spray joint.
17. Be sure to protect the whole surface until it is dried after the work is done.
 
Attention for the construction work
1. The temperature for the construction work should be over 5 °C and the humidity should be less than 80%.
2. The curing work takes long time so before doing the finishing work, be sure to check the weather first. In case it is difficult
to work further because of rain, immediately take a curing action for the existing applied surface which is not dry yet in order
to prevent it from being damaged.
3. Protect the finishing material from any pollutants floating in the air, like dust and smoke, and from weather
(less than 5 °C temperature; over 80% humidity) until it becomes dry.
4. Remove the white part of the concrete surface in advance, and do the construction work when it is completely cured.
5. Repair any polluted or damaged part and do the construction work again.
6. In case it is judged that the pattern has a problem, stop the work, remove out the problem, take corrective actions for
the causes, and then, work.
7. For the repair work, completely remove any pollutants from the existing walls, reinforce the surface with Baro Primer, and
then, do the work.
8. For the surface that is not dry after the mesh finishing or the cement mortar finishing work, don’t do the construction work.
9. don’t do the construction work on the bottom surface that is coated with oil or asphalt.
10. Do not mix with other paints.
11. Prepare sufficient labor and equipment (Sky machine) for consecutive works, and be careful not to have working joints or quality change.
12. Keep all the materials in the place which is out of the direct rays of the sun and well-ventilated
(a dry, cool, and dark place in the temperature of5°C ~ 30°C).
13. In case you have to stop the work while doing the lining work, be careful not to make any spray joint.
 
Special Remark
Classification Painting Method Coverage (Bin) Drying Time Packing Unit
BTS Marble Spray 8-10m² Longer than 48hrs 25kg/Bin
 
PROCESSING FLOW CHART
Process Materials Mixture
(Weight
Ratio)
Consumption
(kg/m²)
Painting Frequency Time Interval (HR) Method
In process Between
process
Final Curing  
Base
Coating
Completely remove impurities in the lower part.
Make even the surface with grooves,cracks, and fractures with the putty.
Under
Coating
Primer 100 0.2-0.4 1   Over 24   Brush,
roller,
Spray
Tap Water 5 - 10
Second
Coating
Marble BTS 100 3-5 2   Over 48   BTS Gun
Diameter
6-8mm
Pressure
3-5kg/
Top
Coating
Barotop 1000 100 0.2-0.4 2     Over 4 Brush,
roller,
Spray
Tap Water 5-10            
 
Property
Category Result Remark
Composition Type 1 Water-soluble  
Specific Gravity 1.6±0.05  
Solid Volume Ratio 77±1%  
Viscosity 80,000±5,000CPS  
pH 7.5±0.5  
Coverage 2.5±0.5 ㎏/㎡  
Coating Thickness 0.8 ~ 1.5㎜  
Drying Time Less than 72 hrs Temp over 20℃,
Humidity lower than 80%
Packing Unit 25㎏/PL